Project Title: WiMAX & RBS Infill Site Installation

Cape Lambert, 8 Mile, West Angelas & Tom Price

WiMAX: 15 meter break back Mast installation including foundation works – 8 Mile & Cape Lambert
RBS infill : Construction of infill RBS sites including 25 Meter mono pole mast foundation works – West Angela’s, Tom Price

Client:

Ansaldo STS (Rio Tinto)
Duration/Year:

September - December 2016
Project Value:

Scope:

– WiMAX: 15 meter break back Mast installation including foundation works – 8 Mile & Cape Lambert
o Excavate to reduced levels and install break back masts in accordance with engineers specifications
o Excavation & Compaction to current standards
o Steel works in accordance with engineers specs
o Concrete pad’s pouring and installation
o Installation of Earth protection
o Installation of break back masts
o Clean and clear site and finish with blue metal

– RBS infill : Construction of infill RBS sites including 25 Meter mono pole mast foundation works – West Angela’s, Tom Price
o Excavate to reduced levels and install in accordance with engineers specifications
o Clearance and grade road and site
o Build up pad in accordance with engineers specifications
o Excavation & Compaction to current standards
o Installation of concrete culverts and pads complete
o Steel works in accordance with engineer’s specs
o Concrete pad’s pouring and installation
o Installation of Earth protection
o Construction of 25 meter mono pole foundation including formworks
o Clean and clear site and finish with blue metal