Project Title: Tom Price Gun Club 286.3km Level Crossing

Tom Price Gun Club

This project involves the upgrading the existing 286.3km passive level crossing (stop signs andlocked gates) to an active level crossing with grade crossing predictor, boom gates, flashing lights, obstruction detection system, floodlights and CCTV.

Client:

Rio Tinto Iron Ore
Duration/Year:

August - November 2017
Project Value:

Scope:

– Procurement of fabrication and construction materials
– Fabrication of Location cases and frames in Malaga
– Factory Testing in Malaga
– Site Civil works including, boring, trenching, pits & pipes, footings & earth grid installation
– Electrical works including, installation of location cases, batteries and solar arrays, installation of ODS, camera & lights, boom gates and flashing lights
– Road improvement works including, grading, sealing, line marking, installation of all signage and Armco barriers
– Commissioning of Level Crossing Control Equipment (Safetran GCP4000)
– Assist with the commissioning of Obstruction Detection Equipment (ODS)