Project Title: FMG T155 Main Line Upgrade

Spanning from Anderson Point to Christmas Creek

Calibre were engaged by Fortescue for the main line expansion of their existing rail network. The Mainline upgrade included expansion of Fortescue’s railway capacity from the Port to Christmas Creek, though duplication of selected sections of the railway (approx 155km duplicated), upgrading the workshop facilities, access and service roads and supporting rail infrastructure.

Client:

Fortescue Metals Group/Calibre
Duration/Year:

October 2011 to Current
Project Value:

Open: Currently at $1 Million
Scope:

  • Construction of trenching, pit and pipe
  • Installation of underbores
  • Vacuum trenching
  • Service locations
Technical Highlights:

  • Mobilising on and off the project within tight timeframes to meet the Clients fluctuating resourcing needs.
  • Utilising the latest in vacuum technology to efficiently locate existing services