Project Title: GE Transport – FMG T155 Mainline Rail Duplication

Port Hedland to Christmas Creek

Upgrade & Installation of track-side asset protection and removal of existing location sites along 152km of FMG Mainline.

Client:

FMG
Duration/Year:

July - November 2013
Project Value:

$3.2 million
Scope:

: Upgrade & Installation of track-side asset protection and removal of existing location sites along 152km of FMG Mainline.

Technical Highlights: